A look ahead for December

Construction activity look ahead up until Christmas:
> Continued road construction to Springfield Drive outside Hayward House to Gate Lodge
> Preparation and installation of piling platform to Forensic Building for piling works to commence in due course.
> Bulk excavation to Non-Forensic Building with muck shifting to park area
> Bulk excavation, ongoing tree removal and hoarding erection to former golf course including topsoil strip
> Further works to establish site compound to the north west end of site
> Construction traffic to utilise new construction entrance off Burntwood Lane
> Christmas shut down from 12:00pm on the 24th December 2019 with site reopening at 8:00am on 2nd January 2020. Security will be present onsite 24/7.
> Preparation works underway for nursery playground relocation

Please click on the image to download a high resolution pdf version

Please click on the image to download a high resolution pdf version

Andrew Thomas