A look ahead for January 2021

Hospital Buildings (delivered by Sir Robert McAlpine)

  • Ongoing construction of concrete frame work to Forensic Hospital Building

  • Ongoing façade installation to Non-Forensic building

  • Fitout and masonry works are ongoing to Non-Forensic building

  • Ongoing construction and structural work to Energy Centre

Civil and Infrastructure (delivered by Sir Robert McAlpine)

  • Outfall drainage installation ongoing in park area

  • Ongoing works to Road 1 located east of Storey Building. Works scheduled for 6 months and traffic management setup to divert traffic to the east of Elizabeth Newton

  • Ongoing works to Road 2 - Storey carpark access road. Access to carpark will be closed

  • Ongoing works to Road 3 - adjacent to the new Care Home (Plot H)

January 2021 Works Location Drawing.jpg

January 2021 SRM Works Location Drawing

Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)

  • Temporary office set up to L-M & parcel E

  • Commence install of temporary electric & water along with security provisions

  • Commence installation of drop curb to access parcel L&M

  • Commence enabling works, pile mat and piling to L,M,B1 & B2

  • Trades commencing on site will include: temp power/water, groundworkers, piling contractors and security

  • Commence enabling works and hard landscaping for marketing suite located in parcel M

Conversion of listed main building to residential - Plot S (delivered by City & Country)

  • Commence the demolition of single storey buildings to the rear of the Main Building

  • Works to the Sales Areas continues

  • Structural alterations continue in the area of the Central Tower and are also now started in Jasmine Tower

  • Externally the stone, brick and roof repairs will continue and scaffolding has been extended to allow these works to commence on further elevations

  • The clock mechanism on the front elevation of the Central tower is to be removed for restoration

  • Whilst the workings are away from site, the clock face itself will be repaired and the numerals repainted

  • Externally, works to the existing trees is due to be concluded to the eastern side of the building

Lisa Baker