A look ahead for January 2021
Hospital Buildings (delivered by Sir Robert McAlpine)
Ongoing construction of concrete frame work to Forensic Hospital Building
Ongoing façade installation to Non-Forensic building
Fitout and masonry works are ongoing to Non-Forensic building
Ongoing construction and structural work to Energy Centre
Civil and Infrastructure (delivered by Sir Robert McAlpine)
Outfall drainage installation ongoing in park area
Ongoing works to Road 1 located east of Storey Building. Works scheduled for 6 months and traffic management setup to divert traffic to the east of Elizabeth Newton
Ongoing works to Road 2 - Storey carpark access road. Access to carpark will be closed
Ongoing works to Road 3 - adjacent to the new Care Home (Plot H)
Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)
Temporary office set up to L-M & parcel E
Commence install of temporary electric & water along with security provisions
Commence installation of drop curb to access parcel L&M
Commence enabling works, pile mat and piling to L,M,B1 & B2
Trades commencing on site will include: temp power/water, groundworkers, piling contractors and security
Commence enabling works and hard landscaping for marketing suite located in parcel M
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Commence the demolition of single storey buildings to the rear of the Main Building
Works to the Sales Areas continues
Structural alterations continue in the area of the Central Tower and are also now started in Jasmine Tower
Externally the stone, brick and roof repairs will continue and scaffolding has been extended to allow these works to commence on further elevations
The clock mechanism on the front elevation of the Central tower is to be removed for restoration
Whilst the workings are away from site, the clock face itself will be repaired and the numerals repainted
Externally, works to the existing trees is due to be concluded to the eastern side of the building