A look ahead for July 2021

Hospital Buildings (Delivered by Sir Robert McAlpine)

  • Ongoing façade installation to Forensic and Non-Forensic buildings

  • Fitout and masonry works to Forensic and Non-Forensic buildings

  • Ongoing mechanical plant installation to Non-Forensic and Forensic buildings

Civil and Infrastructure (Delivered by Sir Robert McAlpine)

  • Works to road 3 from Burntwood Lane – gas and water progressing from Burntwood lane entrance towards Ronald Gibson House this month. Weekend of 3rd/4th July Burntwood Lane entrance will be closed and a diversion will be in place directing the public to the Glenburnie Road entrance.

  • Park works progressing with earthwork movement, drainage and the construction of the ponds. Outfall works will commence at the end of July 2021 on Burntwood Lane and a traffic management plan will be in place. Bowser being used in the park to ensure dust is kept to a minimum.

  • Ongoing works to Road 1 located east of Storey Building. Road 1 lower is closed for public use. Works scheduled for 6 months and traffic management setup to divert traffic to the east of Elizabeth Newton.

  • Ongoing works to Road 2 - Storey carpark access road. Access to carpark will be closed. Road construction progressing outside the nursery, gym and both new hospital buildings, but uninterrupted access will be maintained for both parties through Share Garden. The capping to south of Storey is progressing.

SRM Works Location drawing for July 2021

SRM Works Location drawing for July 2021

Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)

  • Block M superstructure works will commence

  • Block L ground beam works will complete WC 5th July. Ground floor slabs due towards the end of July

  • B1A ground floor slabs 5th July, superstructure to follow from 12th July

  • B1B & B1C – superstructures to continue

  • C1A – superstructure to commence

  • C1B & C1C – ground beam works to complete WC 5th July. Substructure to follow. Ground floor slabs to be installed

  • C2A/B/C – substructure works and ground floor slab to complete

  • E1B & E1C – all materials to be relocated and commencement of reduce dig and foundations

Barratt monthly look ahead drawing - July 2021

Barratt monthly look ahead drawing - July 2021

Conversion of listed main building to residential - Plot S (delivered by City & Country)

  • Sales Suite opened early June.

  • Internal structural alterations to be completed internally.

  • Externally stone, brick and roof repairs continue and additional new windows to be installed in Central East Wing.

  • Internally, plastering to the units in the upper floors of the Central Tower to be completed and commenced in Jasmine Tower.

  • 2nd fixing to commence in the upper units of the Central Tower.

  • Investigations will continue in Orchid Wing and areas to the rear of Central Tower to assist with design works for this next stage of construction.

New care home facility - Plot H (delivered by Lawrence Baker)

  • Building the foundations up out of the ground

  • Foundation and drainage works continue

  • Scaffolding installation to commence

  • External and internal superstructure to continue throughout the summer months

Area of Responsibility Plan