A look ahead for August 2021
Hospital Buildings (Delivered by Sir Robert McAlpine)
Ongoing façade installation to Forensic and Non-Forensic buildings
Fitout and masonry works to Forensic and Non-Forensic buildings
Ongoing mechanical plant installation to Non-Forensic and Forensic buildings
Civil and Infrastructure (Delivered by Sir Robert McAlpine)
Works to road 3 at junction to Burntwood Lane and at the former Community Stores Building for gas and water main connections.
Park works progressing with earthwork movement, drainage and the construction of the ponds. Outfall works are ongoing on Burntwood Lane and a traffic management plan is in place. Bowser being used in the park to ensure dust is kept to a minimum.
Ongoing works to Road 1 located east of Storey Building. Road 1 lower is closed for public use. Works are scheduled to be completed in October 21. Traffic management is currently setup to divert traffic to the east of Elizabeth Newton.
Ongoing works to Road 2 - Storey carpark access road. Access to carpark will be closed. Road construction progressing outside the nursery, gym and both new hospital buildings, but uninterrupted access will be maintained for both parties through Share Garden.
FM shed steel frame works are going to commence end of August 21.
HV electricity statutory undertaker will be laying HV cables into site to Trust Storey Building from Glenburnie Rd.
Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)
Block M superstructure continue
Block L: ground floor slab and commencement of superstructure
B1 – B2 All: superstructure works continue. Mobile crane lifts expected frequently to lift joists and pc slabs
C1 – C2 All – superstructure to commence
E1B & E1C – all materials to be relocated and commencement of reduce dig and foundations
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Internal structural alterations to be completed internally.
Externally stone, brick and roof repairs continue and additional new windows to be installed in Central East Wing.
Internally, plastering to the units in the upper floors of the Central Tower to be completed and commenced in Jasmine Tower.
2nd fixing to commence in the upper units of the Central Tower.
Investigations will continue in Orchid Wing and areas to the rear of Central Tower to assist with design works for this next stage of construction.
New care home facility - Plot H (delivered by Lawrence Baker)
Building the foundations up out of the ground
Foundation and drainage works continue
Ground floor precast installation
Scaffolding installation to commence
External and internal superstructure to continue throughout the summer months