A look ahead for December 2021

Hospital Buildings (Delivered by Sir Robert McAlpine)

  • Trinity (Non-Forensic) building’s façade nearing completion on the North Elevation, other elevations complete. The Shaftesbury (Forensic) façade is ongoing on all elevations.

  • Fitout works to Shaftesbury and Trinity buildings.

  • Mechanical and Electrical works ongoing to Shaftesbury and Trinity buildings.

  • External Scaffold removed apart from the North elevation on the Trinity building.

Civil and Infrastructure (Delivered by Sir Robert McAlpine)

  • Park works progressing with earthwork movements to complete subsoil and topsoil profiling works in the final areas for phase 1. Drainage installation is complete around pond 2 and the construction of the pond 2 is also complete and ready for planting in February. Footpaths to the park are ongoing with around 50% already formed and tarmacked. The pedestrian bridge over pond 2 has been installed. Boundary clearance at the Southern boundary has been reviewed with STEP and Wandsworth Tree Officer. The extent of the clearance has changed following ongoing consultation with various parties. As a minimum there will be further clearance works in December to enable footpath construction to the Southern boundary to tie in to the existing footpath in the existing car park in St Georges Grove.

  • Tree planting has commenced in the park area as planned.

  • Construction is progressing outside the nursery, gym and both new hospital buildings, but uninterrupted access will be maintained for both parties through Share Garden.

  • Works to progress hard landscaping has commenced on Springfield Drive as planned.

Sir Robert McAlpine will shutdown for Christmas from 24th December to 4th January. There will be 24 hour site security.

SRM Works Location drawing for December 2021

Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)

  • Superstructure works to continue B – C

  • B – C inclusive to be at roof level from January up to March 2022

  • Road works to commence B – C up to wearing course

  • Internal M&E works to commence B – C, L & M

  • Superstructure works continue to L&M. M to be at roof level WC 13th December

  • Roof for Block L scheduled early February

  • New marketing suite to ground floor of Block M underway. Launching mid-January 2022

  • Superstructure works to parcel E1 & E2 to commence from next week. these parcels are due for completion December 2022

Barratt London will close on the 24th December. Low risk activities will take place between 29th - 31st December before opening in full on 4th January. 

Barratt monthly look ahead drawing - December 2021

Conversion of listed main building to residential - Plot S (delivered by City & Country)

  • Externally roofing is complete to Jasmine Tower and Jasmine/Lupin link, with works ongoing to Lupin and Rose Towers.

  • Masonry repairs and cleaning to continue to Primrose Tower and commence on garden walls.

  • The installation of new and refurbished cast iron and Crittall style windows is to continue.

  • Decorations to Jasmine Tower and Lupin Tower apartments to continue.

  • Internally, 1st and 2nd fixing to Rose, Primrose and link areas to progress, with plastering to Lupin and Rose Towers completing.

  • Final installations such as floor coverings and white goods to Jasmine Tower to complete and continue in Lupin link units.

  • Lupin Tower lift installation commenced.

  • External service distributions are ongoing to both Phases 1 and 2.

  • Substation to be prepared for livening up.

  • Phase 2 drainage works will continue.

  • Asbestos removal from specific areas of Phase 2 to be removed to allow soft stripping to progress.

City & Country will shut down for Christmas from 23rd December to 4th January.

New care home facility - Plot H (delivered by Lawrence Baker)

  • Complete all the precast planks including the planks to the roof area.

  • Complete the erecting the roof structure by time we close for the Christmas break.

  • Brickwork super structure should be completed to all four gables allowing roof coverings to commence in the new year.

  • M&E works will continue internally up to Christmas.

Lawrence Baker will shutdown for Christmas from 22nd December to 4th January.