A look ahead for June 2022
Hospital Buildings (Delivered by Sir Robert McAlpine)
Trinity (Non-Forensic) building’s façade is now complete. The Shaftesbury (Forensic) façade is still ongoing but nearing completion.
There are ongoing fitout works to Shaftesbury and Trinity hospital buildings.
Mechanical and Electrical works ongoing to both Shaftesbury and Trinity buildings.
All scaffolding has now been struck on both the Trinity and Shaftesbury buildings.
Civil and Infrastructure (Delivered by Sir Robert McAlpine)
Park works will be finishing in June with landscaping and grass seeding being completed. Resin is being applied to all the footpaths.
Tree and shrub planting is complete in the park area and maintenance will be occurring with watering.
Construction is progressing outside Mayfield Nursery and Gymnastics Club and both new hospital buildings, but uninterrupted access will be maintained for both parties through Share Garden.
Works to progress hard landscaping on Springfield Drive is ongoing.
Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)
M
Occupations commence 15th June 2022
Soft landscaping to be completed and area now opened up
L
Internal works continue
Service connections being worked on to footpath on Glenburnie Road
Balconies installed
Remove all hoarding
Block to CML
B – C
Internal works progress
Balcony install to C1A
Hard landscaping continues and will be complete to B within the next month
Soft landscaping commence
C2A to progressive strike to commence
E1/E2
Superstructures continue up to 1st and second floors
D2
D2C superstructure to commence
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Phase 1
First Fix, Close Up, Plaster, 2nd Fix, Decoration and Finals to apartments.
Completion of apartments and communal areas.
Scaffold strike to remaining blocks.
External finishes.
Hard and soft landscaping.
Legal completions.
Occupations
Phase 2
Demolition works ongoing.
Drainage and services.
Scaffold erection and adaptions.
Structural alterations and repairs.
Roofing works.
Masonry repairs and cleaning
New care home facility - Plot H (delivered by Lawrence Baker)
Remove the crane from site. Confirmed for 16th & 17th June
Complete the feature brick openings to the North Elevation – Steels to be erected Monday 20th June
Complete the plastering works to the lower ground floor area
Complete all internal finishes to the bedrooms on the upper two floors
Complete all external hard landscaping to the North & South elevations
Aiming to have all incoming services, water, electricity, and district heating connected
All scaffolding will be removed
All cladding feature panels to be completed.