A look ahead for July 2022
Hospital Buildings (Delivered by Sir Robert McAlpine)
Trinity (Non-Forensic) building’s façade is now complete. The Shaftesbury (Forensic) façade is still ongoing but nearing completion.
There are ongoing fitout works (including painting and decorating) to Shaftesbury and Trinity hospital buildings.
Mechanical and Electrical works ongoing to both Shaftesbury and Trinity buildings.
Civil and Infrastructure (Delivered by Sir Robert McAlpine)
Park works progressing with earthwork movements to complete subsoil and topsoil profiling works in the final areas for phase 1. Works to enable footpath construction to the Southern boundary to tie into the existing footpath in the existing car park in St Georges Grove are ongoing. Lighting columns and associated wiring are being installed and nearing completion.
Tree and shrub planting and maintenance is ongoing in the park area.
Construction is progressing outside Mayfield Nursery and Gymnastics Club and both new hospital buildings, but uninterrupted access will be maintained for both parties through Share Garden.
Works to progress hard landscaping progressing on Springfield Drive is ongoing including the installation of lighting columns and associated wiring.
Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)
M
Occupations continue
Soft landscaping completed
L
Internal works continue
Service connections complete on Glenburnie Road
Remove all hoarding
Block to CML
B – C
Internal works progress
Hard landscaping continues and will be complete to B within the next month
Soft landscaping to continue
C2A to progressive strike to commence
E1/E2
Superstructures continue up to 1st and second floors
D2
D2C superstructure to commence
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Phase 1
First Fix, Close Up, Plaster, 2nd Fix, Decoration and Finals to apartments.
Completion of apartments and communal areas.
Scaffold strike to remaining blocks.
External finishes.
Hard and soft landscaping.
Legal completions.
Occupations
Phase 2
Demolition works ongoing.
Drainage and services.
Scaffold erection and adaptions.
Masonry repairs and cleaning
Window Repairs
Structural alterations and repairs.
Roofing works.
New care home facility - Plot H (delivered by Lawrence Baker)
Complete the feature brick openings to the North Elevation
Complete the plastering works to the lower ground floor area
Continue with internal finishes to the bedrooms on the upper two floors
Continue with external hard landscaping to the North & South elevations
Continue to connect incoming services, water, electricity, and district heating
Continue to remove scaffolding.