A look ahead for July 2022

Hospital Buildings (Delivered by Sir Robert McAlpine)

  • Trinity (Non-Forensic) building’s façade is now complete. The Shaftesbury (Forensic) façade is still ongoing but nearing completion.

  • There are ongoing fitout works (including painting and decorating) to Shaftesbury and Trinity hospital buildings.

  • Mechanical and Electrical works ongoing to both Shaftesbury and Trinity buildings.

Civil and Infrastructure (Delivered by Sir Robert McAlpine)

  • Park works progressing with earthwork movements to complete subsoil and topsoil profiling works in the final areas for phase 1. Works to enable footpath construction to the Southern boundary to tie into the existing footpath in the existing car park in St Georges Grove are ongoing. Lighting columns and associated wiring are being installed and nearing completion.

  • Tree and shrub planting and maintenance is ongoing in the park area.

  • Construction is progressing outside Mayfield Nursery and Gymnastics Club and both new hospital buildings, but uninterrupted access will be maintained for both parties through Share Garden.

  • Works to progress hard landscaping progressing on Springfield Drive is ongoing including the installation of lighting columns and associated wiring.

SRM Works Location drawing for July 2022

Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)

  • M

    • Occupations continue

    • Soft landscaping completed

  • L

    • Internal works continue

    • Service connections complete on Glenburnie Road

    • Remove all hoarding

    • Block to CML

  • B – C

    • Internal works progress

    • Hard landscaping continues and will be complete to B within the next month

    • Soft landscaping to continue

    • C2A to progressive strike to commence

  • E1/E2

    • Superstructures continue up to 1st and second floors

  • D2

    • D2C superstructure to commence

Barratt detailed Execution Plan

Conversion of listed main building to residential - Plot S (delivered by City & Country)

Phase 1

  • First Fix, Close Up, Plaster, 2nd Fix, Decoration and Finals to apartments.

  • Completion of apartments and communal areas.

  • Scaffold strike to remaining blocks.

  • External finishes.

  • Hard and soft landscaping.

  • Legal completions.

  • Occupations

Phase 2

  • Demolition works ongoing.

  • Drainage and services.

  • Scaffold erection and adaptions.

  • Masonry repairs and cleaning

  • Window Repairs

  • Structural alterations and repairs.

  • Roofing works.

New care home facility - Plot H (delivered by Lawrence Baker)

  • Complete the feature brick openings to the North Elevation

  • Complete the plastering works to the lower ground floor area

  • Continue with internal finishes to the bedrooms on the upper two floors

  • Continue with external hard landscaping to the North & South elevations

  • Continue to connect incoming services, water, electricity, and district heating

  • Continue to remove scaffolding.

Area of Responsibility Plan

Lisa Baker