A look ahead for October 2022
Hospital Buildings (Delivered by Sir Robert McAlpine)
There are ongoing fitout works (including painting and decorating) to Shaftesbury and Trinity hospital buildings that are ongoing but both nearing completion in some areas
Some areas of the Trinity building have been handed over to the Trust for training purposes. Handover of the full building is due for completion within the period.
Mechanical and Electrical works ongoing to both Shaftesbury and Trinity buildings which includes commissioning and testing.
Civil and Infrastructure (Delivered by Sir Robert McAlpine)
The park is completed and handed over for its maturing period.
Construction is progressing outside Mayfield Nursery and Gymnastics Club and both new hospital buildings, but uninterrupted access will be maintained for both parties through Share Garden until the public access is opened on Springfield Drive at the end of the month.
The hard landscaping on Springfield Drive and Chapel Square is nearing completion with finishing the granite, paving, lighting columns and trees. Public access is planned to be opened at the end of the month.
Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)
Block L & M now fully occupied and external landscaping to be complete by 30 September
Block B1 occupied.
Block B2/C1 – CML and occupation by 28 October
Block C2 – CML & Occupation by 28 October
Parcel E1 & E2 – External façade ongoing with internal fit-out commencing within next 2 weeks.
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Phase 1
Close Up, Plaster, 2nd Fix, Decoration and Finals to apartments.
Completion of apartments and communal areas.
Scaffold strike to remaining blocks.
External finishes.
Hard and soft landscaping.
Legal completions.
Completed on 22no plots to date.
Phase 2
Asbestos removal is complete.
Soft strip and demolition works ongoing.
Drainage and services.
Scaffold erection and adaptions.
Structural alterations and repairs.
Roofing works.
Masonry repairs and cleaning.
Commence internal fit out
New care home facility - Plot H (delivered by Lawrence Baker)
Lawrence Baker intend to complete all the works internally and externally ahead of handing the building over to their client mid-October.
Currently they are working on the external landscaping and internal finishes. Fitout will be completed by the 7th October.