A look ahead for November 2022
Hospital Buildings (Delivered by Sir Robert McAlpine)
There are ongoing and final fitout works (including painting, decorating and furnishings) to Shaftesbury and Trinity hospital buildings that are ongoing but both nearing completion in some areas
Some areas of the Trinity building have been handed over to the Trust including carparks. Full handover of the Trinity building is due for completion within the period.
Mechanical and Electrical works ongoing to both Shaftesbury and Trinity buildings which includes commissioning and testing prior to handovers.
Civil and Infrastructure (Delivered by Sir Robert McAlpine)
The park is completed and handed over for its maturing period.
Construction is nearing completion outside Mayfield Nursery and Gymnastics Club and both new hospital buildings, but uninterrupted access will be maintained for both parties through Share Garden until the public access is opened on Springfield Drive at the end of the month.
The hard landscaping on Springfield Drive and Chapel Square is nearing completion with finishing the feature lighting in Chapel Square. Public access is planned to be opened at the end of the month.
Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)
Block L & M now fully occupied and external landscaping completed.
Block B1 & B2 Occupied.
Block C1 & C2 external landscaping complete by 11 November.
Parcel E1 & E2 – External façade ongoing with internal fit-out commenced to E1B.
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Phase 1
Close Up, Plaster, 2nd Fix, Decoration and Finals to apartments.
Completion of apartments and communal areas.
Scaffold strike to remaining blocks.
External finishes.
Hard and soft landscaping.
Legal completions.
Completed on 26no plots to date.
Phase 2
Asbestos removal is complete.
Soft strip and demolition works ongoing.
Drainage and services.
Scaffold erection and adaptions.
Structural alterations and repairs.
Roofing works.
Masonry repairs and cleaning.
Commence internal fit out
New care home facility - Plot H (delivered by Lawrence Baker)
Lawrence Baker team is completing final elements of the care home and preparing for handover to the client.