A look ahead for December 2022
Hospital Buildings (Delivered by Sir Robert McAlpine)
Following the handover of the completed Trinity building, there are ongoing and final fitout works (including painting, decorating and furnishings) to Shaftesbury hospital buildings that is nearing completion.
Mechanical and Electrical works ongoing to the Shaftesbury building which includes commissioning and testing prior to handover.
Civil and Infrastructure (Delivered by Sir Robert McAlpine)
The park is completed and handed over for its maturing period.
Construction is completed outside Mayfield Nursery, Gymnastics Club and Trinity hospital building. Public access is opened on Springfield Drive and Chapel Square in early December 2022.
The entrance to Burntwood Lane is closed from 5th December for 28 weeks and access is provided further north on Burntwood Lane. This is to allow the new road construction and the junction works to commence in early 2023.
The pavilion building in Park A is progressing with the foundations and steelwork will be erected mid December 2022.
Plot A - Welfare progressing with site cabin being delivered early December 2022.
Christmas closedown is from Friday 23rd December 2022 until Tuesday 3rd January 2023.
Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)
Blocks L,M are fully occupied
Blocks B1 & B2 partially occupied (houses and duplex units predominantly)
Block C2a is fully occupied
Blocks C1 and C2 second fix works and internal snagging ongoing
Blocks E1 & E2 – External façade ongoing with the first fix fit out to E1B
Christmas period working hours - main construction shutdown from Friday 23rd December 2022 until Tuesday 3rd January 2023.
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Phase 1
Close Up, Plaster, 2nd Fix, Decoration and Finals to apartments.
Completion of apartments and communal areas.
Scaffold strike to remaining areas.
External finishes.
Hard and soft landscaping.
Legal completions.
Completed on 32no plots to date.
Phase 2
Soft strip and demolition works ongoing.
Drainage and services.
Scaffold erection and adaptions.
Structural alterations and repairs.
Roofing works.
Re-Facing of brickwork elevations
Masonry repairs and cleaning.
Commence internal fit out
Christmas closedown is from Friday 23rd December 2022 until Tuesday 3rd January 2023.
New care home facility - Plot H (delivered by Lawrence Baker)
Lawrence Baker team is completing final elements of the care home and preparing for handover to the client.