A look ahead for January 2023
Hospital Buildings (Delivered by Sir Robert McAlpine)
Following the handover of the completed Trinity building, there are ongoing and final fitout works (including painting, decorating and furnishings) to Shaftesbury hospital buildings that is nearing completion.
Mechanical and Electrical works ongoing to the Shaftesbury building which includes commissioning and testing prior to handover.
Civil and Infrastructure (Delivered by Sir Robert McAlpine)
The park is completed and handed over for its maturing period.
Public access is opened on Springfield Drive and Chapel Square.
The entrance to Burntwood Lane is closed and access is provided further north on Burntwood Lane. This is to allow the new road construction to progress and the junction works to commence in January 2023.
The pavilion building in Park A is progressing with the ground floor slab and muck movement will commence mid January 2023.
Plot A - Welfare progressing with site cabin installation complete and concrete paths and tarmac to be completed this month.
Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)
Blocks L and M are fully occupied
Block B1 partially occupied (houses and duplex units predominantly), January handovers to the remaining plots
Blocks B2, C1 and C2 second fix works, decorations and internal snagging ongoing
Block C2a is fully occupied
Blocks E1 and E2 – External façade works ongoing with the first fix fit out to E1B
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Phase 1
Close Up, Plaster, 2nd Fix, Decoration and Finals to apartments.
Completion of apartments and communal areas.
Scaffold removal to remaining areas.
External finishes.
Hard and soft landscaping.
Legal completions.
Completed on 39no plots to date.
Phase 2
Soft strip and demolition works ongoing.
Drainage and services.
Scaffold erection and adaptions.
Structural alterations and repairs.
Roofing works.
Re-Facing of brickwork elevations
Masonry repairs and cleaning.
Commence internal fit out
New care home facility - Plot H (delivered by Lawrence Baker)
Lawrence Baker team is completing final elements of the care home and preparing for handover to the client.