A look ahead for May 2023
Hospital Buildings (Delivered by Sir Robert McAlpine)
Following the handover of the Trinity building, there are final fitout works (including painting, decorating and furnishings) to Shaftesbury hospital building.
Mechanical and Electrical works are still ongoing to the Shaftesbury building which includes commissioning and testing prior to handover.
Civil and Infrastructure (Delivered by Sir Robert McAlpine)
The park is completed and handed over for its maturing period.
Public access is opened on Springfield Drive and Chapel Square. Car parks in the new hospitals are open and car park B is closed to allow Park C to progress.
Plot A – SRM’s new welfare is now up and running and will be located here until the end of the year.
The entrance to Burntwood Lane is closed and access is provided further north on Burntwood Lane. This is to allow the new road construction to be completed and open up end of May/early June 2023. The junction works is now progressing.
The pavilion building in Park A is progressing with roof works and muck movement is ongoing.
Ronald Gibson House demolition is progressing. The structure has been removed and foundations are being removed.
Ruskin lane works to start this month, which will allow the G1 bus to return to Springfield Village at the end of the Summer.
Harewood House demolition has commenced with the asbestos survey. Soft strip to commence following the removal of the licenced asbestos this month.
Park C muck shift works progressing.
Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)
Blocks L and M are fully occupied
Block B1 is fully occupied
Blocks B2, C1 and C2 handovers ongoing
Block C2a is fully occupied
Blocks E1 and E2 – External façade works ongoing with the second fix and decorations to E1 parcel
Groundworks continue to E1 parcel blocks
Block D1a and D2c houses - Superstructure works ongoing
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Phase 1
Plaster, 2nd Fix, Decoration and Finals to remaining apartments.
Completion of apartments and communal areas.
Scaffold removal to remaining areas.
External finishes.
Legal completions.
Occupations
Completed on 45no plots to date.
Phase 2
Soft strip and demolition works ongoing.
Drainage and services.
Scaffold erection and adaptions.
Structural alterations and repairs.
Roofing works.
Re-Facing of brickwork elevations.
Masonry repairs and cleaning.
Internal fit out ongoing to ‘Kitchen Block’ area.