Construction underway on the new care home at Springfield Village

Contractor Lawrence Baker is progressing well with the new care home facility for Brendoncare on plot H (click here for plot plan) of the Springfield site.

Works over the coming month include:

  • Completion of the site set up: welfare and office units

  • Completion of the excavation and concreting to the west wing foundations

  • Build and completion of the steel structure for the retaining wall in the foundations of the west wing

  • Spoil removal to allow access to continue with excavations of the east wing

  • Forming of the crane base and erection of the crane

  • Commencement of the first foundation blockwork

A visualisation of the completed care home building is shown below.