Out of hours works - 21st and 23rd February 2023

Overnight concrete pours to the Pavilion will be undertaken by Sir Robert McAlpine during the nights of Tuesday 21/02/23 and Thursday 23/02/23, from 18.00-08.00 Note: these dates are subject to change depending on the weather conditions.

Due to the type of concrete and polished finished, the pours are required to be undertaken at night due to the chemical reaction of the concrete. The concrete needs to have commenced curing to allow the team to stand on it to apply the finish. There is a limited window in which the finish can be successfully applied. Too early the finish is poor, too late and the project wont achieve the finish.

Sir Robert McAlpine would not classify the applied works to be ‘noisy works’. Additionally, they are located away from sensitive receptors and are not anticipated to be audible at the site boundary.