A look ahead for November 2023

Hospital Buildings (Delivered by Sir Robert McAlpine)

  • The Shaftesbury building was handed over to the client on Friday the 29th of September. 

Civil and Infrastructure (Delivered by Sir Robert McAlpine)

  • The park (area B) is open.

  • Public access is opened on Springfield Drive and Chapel Square.  Car parks in the new hospitals are open.

  • Plot A – SRM’s new welfare is now up and running and will be located here until the end of the year.

  • The entrance to Burntwood Lane is closed and vehicle access is provided further north on Burntwood Lane.  Pedestrian access is now available along the north of the opened park. The new road construction and remedials are completed.  We are waiting on sign off from Wandsworth Council and will have the entrance opened by the end of November 2023. 

  • Hard and soft landscaping is progressing in Park A.  Further trees will be planted this month.  The youth shelter is installed.  The pavilion works will commence this month.

  • Ruskin lane works are completed, which will allow the G1 bus to return to Springfield Village in end of November/early December 2023, once the entrance to Burntwood Lane is open.

  • Harewood House demolition is completed.  Further remedial works will be required prior to handover to the House Developer in the New Year.

  • Park C muck shift is nearing completion.  Pathways and soft landscaping are progressing.  Tree planting will commence this month.  Amphitheatre seating has commenced and is progressing well.

  • Road 4; Lapidge Drive is completed and open.  The next section of roads will be completed by the end of the month, to allow the last section of road to commence.

  • The last substation within the development will commence at the end of the month outside Phoenix Building.

SRM Works Location drawing for November 2023

Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)

  • Blocks L, M, B1, C2a, B2a, C1a are fully occupied

  • All PA Housing units now fully handed over including 5 full mobility units

  • Occupations ongoing to E1a, E1c and E1b

  • Service install ongoing to E2 parcel blocks

  • E2 Power on due November 23

  • E2 internal fit out underway

  • Temporary welfare situated in E2 parcel to be removed to enable external works progression

  • New Phase 2 welfare will be in operation and used from mid-November

  • Block D1A & D1B, brickwork on-going

  • D1C ground beams poured

  • D2B ground beam poured

  • Floors for both D1C and D2B due w/c 13/11/23

  • D2C internal fit out started, power on due w/c 6/11/23

Conversion of listed main building to residential - Plot S (delivered by City & Country)

Phase 1 

Complete

Phase 2

  • Structural alteration works ongoing to the Engineering Block and Boiler House.

  • Scaffold erection and adaptions.

  • Structural alterations and repairs.

  • Roofing works to Boiler house, Engineering Tower, Dormitory block and Orchid Wing.

  • Re-Facing of brickwork elevations.

  • Masonry repairs and cleaning.

  • Window refurbishment

  • Steelwork and floor construction to Engineering tower.

  • Internal fit out ongoing to Kitchen Block’ area.

  • Test and commissioning

  • Finals and Inspections to the Kitchen Block apartments

  • Handovers and completions within kitchen block