A look ahead for December 2023

Hospital Buildings (Delivered by Sir Robert McAlpine)

  • Both Hospital Buildings are open for use.

Civil and Infrastructure (Delivered by Sir Robert McAlpine)

  • The park (area B) is open.

  • Public access is opened on Springfield Drive and Chapel Square.  Car parks in the new hospitals are open.

  • Plot A – SRM’s new welfare is now up and running and will be located here until the end of the year.

  • The entrance to Burntwood Lane is OPEN for both vehicle and pedestrian access.

  • The pavilion works in Park A is progressing with fit out works.  Façade will be installed in the new year.  Drainage diversion works have commenced ahead of the Belvedere construction in the new year.  Soft landscaping will start again in February/March 2024.

  • Ruskin lane and Bicknell Way works are completed, which allows the G1 bus to return to Springfield Village.

  • Harewood House demolition is completed.  Further remedial works will be required prior to handover to the House Developer in the New Year.

  • The amphitheatre seating is nearing completion this month and muck shift will recommence to allow final pathways to be progressed in the new year.  Soft landscaping will start again in February/March 2024.

  • Road 4; Lapidge Drive is completed and open for access for C&C residents.  The final section of road has commenced.

  • The last substation within the development has commenced outside Phoenix Building.

SRM Works Location drawing for December 2023

Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)

  • D2C CMLs gained, occupation expected w/c 18/12/23

  • All PA Housing units now fully handed over including 5 full mobility units

  • Occupations ongoing to E1a, E1c and E1b

  • Service install ongoing to E2 parcel blocks

  • E2 Power on moved to January 24

  • E2 internal fit out underway

  • E2 Temporary welfare removed, now removed hardscaping due to commence Jan 24

  • E2 court yard landscaping works commenced

  • New Phase 2 welfare/site office now occupied

  • D1B, brickwork on-going, 1st floor joists installed

  • D1A brickwork on-going 2nd floor concrete floors due Feb 24

  • D1C ground beams poured, brickwork started

  • D2B ground beam poured

  • Floors for both D1C and D2B due w/c 13/11/23, installed

Conversion of listed main building to residential - Plot S (delivered by City & Country)

Phase 1 

Complete

Phase 2

  • Structural alteration works ongoing to the Engineering Block and Boiler House.

  • Scaffold erection and adaptions.

  • Structural alterations and repairs.

  • Roofing works to Boiler house, Engineering Tower, Dormitory block and Orchid Wing.

  • Re-Facing of brickwork elevations.

  • Masonry repairs and cleaning.

  • Window refurbishment

  • Steelwork and floor construction to Engineering tower.

  • Internal fit out ongoing to Kitchen Block’ area.

  • Test and commissioning

  • Finals and Inspections to the Kitchen Block apartments

  • Handovers and completions within kitchen block

  • Internal fit out to Dormitory wing