A look ahead for February 2024
Hospital Buildings (Delivered by Sir Robert McAlpine)
Both Hospital Buildings are open for use.
Civil and Infrastructure (Delivered by Sir Robert McAlpine)
The park (area B) is open.
Public access is opened on Springfield Drive and Chapel Square. Car parks in the new hospitals are open.
The entrance to Burntwood Lane is OPEN for both vehicle and pedestrian access.
The pavilion works in Park A is progressing with fit out works, MEP and façade. Drainage diversion works are completed and the Belvedere construction along with pathways will be completed at the end of February/early March 2024. Soft landscaping has recommenced with tree and plant installation. 5-11 play equipment will commence this month.
Ruskin lane and Bicknell Way works are completed, which allows the G1 bus to return to Springfield Village.
Harewood House demolition is completed. Further remedial works are being completed to allow handover to the House Developer this month.
Park C works is progressing with finishing off the soft landscaping around the amphitheatre seating area and pathways.
District heating works down to X,Y,Z plot will progress.
Road 4; Lapidge Drive is completed and open for access for C&C residents. The final section of road will be completed this month.
The last substation within the development is progressing outside Phoenix Building.
Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)
D2C Occupations started in December 23, ongoing though February 24
All PA Housing units now fully handed over including 5 full mobility units, end of year defects have now started
E1 parcel now fully occupied or sold
E2 parcel services are now all live
E2 internal fit progressing, currently being 2nd fixed and flooring
E2 Court yard 80% complete, works to the front of E2C has commenced
New Phase 2 welfare/site office now occupied
D1A brick and blockwork at mis way on level 1 2nd floor concrete floors due W/C 19/2/24
D1B, low section is at roof level, roof to high level expected early March
D1C 1st floor joist expected to commence W/C 5/2/24
D2B ground floor block and blockwork in progress
D2A ground floor brick and blockwork in progress
D parcel road base cause is complete
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Phase 1
Complete
Phase 2
Structural alteration works ongoing to the Engineering Block and Boiler House.
Scaffold erection and adaptions.
Structural alterations and repairs.
Roofing works to Boiler house, Engineering Tower, Dormitory block and Orchid Wing.
Re-Facing of brickwork elevations.
Masonry repairs and cleaning.
Window refurbishment
Steelwork and floor construction to Engineering tower.
Commence fit out to Engineering Tower
Internal fit out ongoing to Kitchen Block’ area.
Test and commissioning
Finals and Inspections to the Kitchen Block apartments
Handovers and completions within kitchen block
Internal fit out to Dormitory wing
Scaffold Strike to various areas