A look ahead for March 2024
Hospital Buildings (Delivered by Sir Robert McAlpine)
Both Hospital Buildings are open for use.
Civil and Infrastructure (Delivered by Sir Robert McAlpine)
The park (area B) is open.
Public access is opened on Springfield Drive and Chapel Square. Car parks in the new hospitals are open.
The entrance to Burntwood Lane is OPEN for both vehicle and pedestrian access.
Park area A is nearing completion with the Belvedere and pathways being finished. Soft landscaping is progressing, with completion mid Spring 2024. 5-11 play equipment has commenced. The pavilion works is progressing with fit out works, MEP and timber façade.
Harewood House plot to be handed over to the House Developer this month.
Park C works will commence again, now that Hemiko have installed the district heating pipework. Play equipment and soft landscaping to progress.
District heating works down to X,Y,Z plot is progressing.
Road 4; Lapidge Drive is completed and open for access to everyone.
The last substation within the development is progressing outside Phoenix Building.
Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)
D2C Occupations started in December 23, ongoing though February 24
E1 parcel now fully occupied or sold
E2 parcel district heating is now live
E2 internal fit progressing, currently 35 units are painted with commissioning and carpets ongoing
E2 Court yard play area is complete and soft landscaping due to start, works to the front now 805 complete with tarmac due towards the end of March
D1A 2nd floor slab installed brick and blockwork to level 2 to commence
D1B, scaffold strike to start mid-March
D1C 2nd floor and low level roof joist expected to commence Mid-March
D2B 2nd floor and low level roof joist expected to commence end of March
D2A ground floor brick and blockwork in progress 2nd floor concrete slab expected at the end of March
D parcel road base cause is complete
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Phase 1
Complete
Phase 2
Structural alteration works ongoing to the Engineering Block and Boiler House.
Scaffold erection and adaptions.
Structural alterations and repairs.
Roofing works to Boiler house, Engineering Tower, Dormitory block and Orchid Wing.
Re-Facing of brickwork elevations.
Masonry repairs and cleaning.
Window refurbishment
Steelwork and floor construction to Engineering tower.
Commence fit out to Engineering Tower
Internal fit out ongoing to Kitchen Block’ area.
Test and commissioning
Finals and Inspections to the Kitchen Block apartments
Handovers and completions within kitchen block
Internal fit out to Dormitory wing
Scaffold Strike to various areas