A look ahead for May 2024
Hospital Buildings (Delivered by Sir Robert McAlpine)
Both Hospital Buildings are open for use.
Civil and Infrastructure (Delivered by Sir Robert McAlpine)
The park (area B) is open.
Public access is opened on Springfield Drive and Chapel Square. Car parks in the new hospitals are open.
The entrance to Burntwood Lane is OPEN for both vehicle and pedestrian access.
Park area A is nearing completion with soft landscaping, play equipment and resin works to pathways being completed. The pavilion is nearing completion too. Park area A is due to open October 2024, after a period of maturing.
Harewood House plot to be handed over to the House Developer in June 2024.
Park C works are progressing with soft landscaping, gym stations and pathways. Park area C is due to open October 2024, after a period of maturing.
District heating works down to X,Y,Z plot is progressing.
Road 4; Lapidge Drive is completed and open for access to everyone.
The last substation build within the development is completed outside Phoenix Building. Infrastructure works is progressing to allow energisation in July 2024.
Residential Phase - Plots B-E and L&M (delivered by Barratt London)
D2C Occupied
E1 All units sold, completions to the last units will continue through May
E2 Has been given CML (Council of Mortgage Lenders), hand over to client end of May
E2 Court yard play area is complete.
D1A 3rd floor slab installed brick and blockwork commenced to roof level, roof slab Mid May
D1B, Internal fit out commenced, external landscaping to from also commenced
D1C Internal fit out commenced, scaffold strike to start early may
D2B 1st fix commenced scaffold strike to start early may
D2A 1st floor slab installed, brick and block work in progress to level 2 slab expected Mid May
D parcel road base cause is complete
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Phase 1
Complete
Phase 2
Structural alteration works ongoing to the Engineering Block and Boiler House.
Scaffold erection and adaptions.
Structural alterations and repairs.
Roofing works to Boiler house, Engineering Tower, Dormitory block and Orchid Wing.
Re-Facing of brickwork elevations.
Masonry repairs and cleaning.
Window refurbishment
Steelwork and floor construction to Engineering tower.
Commence fit out to Engineering Tower
Internal fit out ongoing to Kitchen Block’ area.
Test and commissioning
Finals and Inspections to the Kitchen Block apartments
Handovers and completions within kitchen block
Internal fit out to Dormitory wing
Scaffold Strike to various areas.
Next phase of new build residential Plots G, P, Q and F (delivered by London Square)
Block P
Continuing with the basements to the houses.
Commencing the retraction of the sheet piles to the basement excavations on the houses.
Commencing substructure brickwork to the apartment block
Installing the beam and block floor to the apartment block.
Block Q
Commencing the basement excavation to the houses.
Commencing basement slabs and walls to the houses.
Block G
Removing the substation that feeds the Trust and SRM (as long as there are no hick ups with Power On)
Continuing with the ground beams.
Commencing brickwork to G2/3.
Block F
No works are envisaged to take place as we are awaiting SRM to divert the gas main which is due to be completed mid June.
We’d like to advise you that London Square’s sales suite is now open.
A beautiful collection of 1, 2 & 3 bedroom apartments and 4 & 5 bedroom houses nestled beside the new 32 acre park with completions due from summer 2025.
Details can be found on their website here.