A look ahead for August & September
Civil and Infrastructure (Delivered by Sir Robert McAlpine)
The park (area B) is open.
Public access is opened on Springfield Drive and Chapel Square. Car parks in the new hospitals are open.
The entrance to Burntwood Lane is OPEN for both vehicle and pedestrian access.
Park area A is completed and currently maturing. The pavilion is nearing completion too. Park area A is due to open October 2024, after a period of maturing.
Harewood House plot handed over to the House Developer (London Square) in June 2024.
Park C works is complete except for seeding which has been deferred to ensure seeding occurs at the correct time of the year. Park area C is due to open October 2024, with areas cordoned off to allow maturing.
District heating works down to X,Y,Z plot is progressing and reinstatement of footpath is nearly complete. Will be completed early August 2024.
Road 4; Lapidge Drive is completed and open for access to everyone.
The last substation build within the development is completed outside Phoenix Building. Infrastructure works is completed to allow energisation early August 2024.
Residential Phase - Plots B-E and L&M (delivered by Barratt London)
D2C Occupied
E1 Occupied
E2 Occupied
D1A internal fit out has commenced Balcony install to commence late July, Granit paving commenced, Handover to Sainsbury End of August
D1B, Occupied
D1C Occupied
D2B Occupied
D2A Roof slab due early August, fit out to commence in September
D parcel (Cherry mews) Open
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Phase 1
Complete
Phase 2
Scaffold adaptions and strike
Structural alterations and repairs
Roofing works to Orchid Wing
Re-Facing of brickwork elevations
Masonry repairs and cleaning
Window refurbishment
Test and commissioning
Handovers and completions within Kitchen Block, Engineering Tower & Dormitory Wing
Internal fit out ongoing to Dormitory and Orchid wing
Hard & Soft Landscaping.
Next phase of new build residential Plots G, P, Q and F (delivered by London Square)
Block P
House basements complete.
Commenced super structure brickwork to the apartment block
Installing the beam and block floor to the apartment block.
Commenced setting out & 2nd lift scaffold.
Block Q
Commenced the basement excavation to the houses.
Commenced basement slabs and walls to the houses.
Ground beams to block Q1 & Q2 apartment block in progress
Block G
Existing substation has been deenergised and removed and the new substation energised and in use.
Installing the beam and block floor to the G1 & G4 apartment block.
Continue brickwork to G2/3.
Block F
SRM handed over block F to LSQ, with demolition and piling works to commence.