A look ahead for August & September

Civil and Infrastructure (Delivered by Sir Robert McAlpine)

  • The park (area B) is open.

  • Public access is opened on Springfield Drive and Chapel Square.  Car parks in the new hospitals are open.

  • The entrance to Burntwood Lane is OPEN for both vehicle and pedestrian access.

  • Park area A is completed and currently maturing.  The pavilion is nearing completion too.  Park area A is due to open October 2024, after a period of maturing.

  • Harewood House plot handed over to the House Developer (London Square) in June 2024.

  • Park C works is complete except for seeding which has been deferred to ensure seeding occurs at the correct time of the year.  Park area C is due to open October 2024, with areas cordoned off to allow maturing.

  • District heating works down to X,Y,Z plot is progressing and reinstatement of footpath is nearly complete. Will be completed early August 2024.

  • Road 4; Lapidge Drive is completed and open for access to everyone.

  • The last substation build within the development is completed outside Phoenix Building.  Infrastructure works is completed to allow energisation early August 2024.

Residential Phase - Plots B-E and L&M (delivered by Barratt London)

  • D2C Occupied

  • E1 Occupied

  • E2 Occupied

  • D1A internal fit out has commenced Balcony install to commence late July, Granit paving commenced, Handover to Sainsbury End of August

  • D1B, Occupied

  • D1C Occupied

  • D2B Occupied

  • D2A Roof slab due early August, fit out to commence in September

  • D parcel  (Cherry mews) Open

Conversion of listed main building to residential - Plot S (delivered by City & Country)

Phase 1 

Complete

Phase 2

  • Scaffold adaptions and strike

  • Structural alterations and repairs

  • Roofing works to  Orchid Wing

  • Re-Facing of brickwork elevations

  • Masonry repairs and cleaning

  • Window refurbishment

  • Test and commissioning

  • Handovers and completions within Kitchen Block, Engineering Tower & Dormitory Wing

  • Internal fit out ongoing to Dormitory and Orchid wing

  • Hard & Soft Landscaping.

Next phase of new build residential Plots G, P, Q and F (delivered by London Square)

Block P

  • House basements complete.

  • Commenced super structure brickwork to the apartment block

  • Installing the beam and block floor to the apartment block.

  • Commenced setting out & 2nd lift scaffold.

Block Q

  • Commenced the basement excavation to the houses.

  • Commenced basement slabs and walls to the houses.

  • Ground beams to block Q1 & Q2 apartment block in progress

Block G

  • Existing substation has been deenergised and removed and the new substation energised and in use.

  • Installing the beam and block floor to the G1 & G4 apartment block.

  • Continue brickwork to G2/3.

Block F

  • SRM handed over block F to LSQ, with demolition and piling works to commence.

External CGI from London Square Apartment overlooking Springfield Park