A look ahead for October & November
Civil and Infrastructure (Delivered by Sir Robert McAlpine)
The park is open (with areas in Park area C cordoned off to allow maturing).
Residential Phase - Plots B-E and L&M (delivered by Barratt London)
Total number of plots sold to date is 243 with 35 plots remaining.
Primrose House (D2A) is fully occupied.
Works taking place during October and November: D1A internal fit out continues to complete mid-October, D2A both internal and external work progressing,
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Phase 1 is complete.
Works continue on Phase 2, which include:
Demolition to the final section of existing roof to Orchid Wing
Installation of new steel and timber frame to roof to Orchid Wing
Re-Facing of brickwork elevations
Masonry repairs and cleaning
Window refurbishment
Test and commissioning to apartments within Kitchen Block, Engineering Tower & Dormitory Wing apartments
Internal fit out and commisioning to communal areas above
Building Control / warranty provider inspections and certification for units ready to handover to purchasers in Kitchen Block, Engineering Tower & Dormitory Wing
Hard & Soft Landscaping to external areas
Currently on Phase 3 City & Country are doing preparation works for a new office facility for Share Garden in anticipation of decanting from Phase 3 areas. There are also improvements to access and hoarding works in advance of construction activity starting on site.
Next phase of new build residential Plots G, P, Q and F (delivered by London Square)
Sales
· 8 - plots have currently been sold which include 4 x two bed apartments and 4 x houses.
Block P
Completion of 2nd floor structural balcony brackets
Commence 5th lift brick work
Commence roof trusses to plots 230 to 233
Commence 2nd floor joists to plots 234 to 236
Commence 1st floor joists to plots 237 to 240
Block Q
Commence 1st lift brick work
Commence 1st lift scaffold
Commence district heating to Q houses
Commence 1st lift brick work to plots 242 to 244
Commence the installation of services & permeable road to plots 242 to 250
Block G
Commence 3rd lift brick work to block G2 & 3
Installation of block G1 & 4, 1st floor pre-cast planks
Continue brickwork to G2/3.
Block F
Commence block & beam to both block & houses
Commence external services and drainage.
Installation of tower crane on 28/11/24