A look ahead for April 2020

Infrastructure

  • Plot remediation and hoardings to be completed for plots B1-E2

  • Gas and electrical diversions to progress

  • Site compound works to be completed

  • Demolition of Golf Club and decommissioned Substation in plot D2

  • Ongoing road construction with the first road closure adjacent to Share Garden

Hospitals

  • Completion of all bulk excavation works following Gas and HV service diversions

  • Drainage and concrete works to the Non-Forensic and Forensic buildings to progress

  • Ongoing works to the Non-Forensic superstructure

  • Preparation works for the energy centre will start