Late works in May 2020

SRM will be conducting a number of large concrete pours over the coming year that will require a brushed finish to the carpark levels. This applies to all 3 levels of the Forensic Building and lower ground floor of the Non-Forensic Building. The concrete pour itself will happen between normal working hours of 8am to 6pm. The brushing however will need to wait for the concrete to cure sufficiently and hence will likely carry on till 11pm, midnight at the latest. The brushing itself will be undertaken manually so no noise is generated. Lighting towers will be used to light the work area and positioned is such a way as to not disturb local residents and minimise light pollution.

This week SRM plan to carry out the works as below:

NON-FORENSIC
Monday 18/05 - SPR02 Raft Slab

FORENSIC
Thursday 21/05 - SPR01 Raft Slab

Thursday 28/05 - SPR01 Raft Slab

Friday 29/05 - SPR01 Raft Slab



Lisa Baker