A look ahead for May 2020
Hospital Buildings
Ongoing foundation and concrete frame works to Forensic and Non-Forensic hospital buildings
Civil and Infrastructure
Commence new road construction within current road closure adjacent to plots P and Q
Finish SRM site compound and yard area
HV diversion to plot E2 and forensic building footprint are provisionally planned WC 30/05
LV connections to building plots B to E followed by completion of site hoarding
Demolition of old Golf Club House and asbestos removal, soft strip and demolition of Penrose (Building 18)