Hospital Buildings

  • Ongoing foundation and concrete frame works to Forensic and Non-Forensic hospital buildings

Civil and Infrastructure

  • Commence new road construction within current road closure adjacent to plots P and Q

  • Finish SRM site compound and yard area

  • HV diversion to plot E2 and forensic building footprint are provisionally planned WC 30/05

  • LV connections to building plots B to E followed by completion of site hoarding

  • Demolition of old Golf Club House and asbestos removal, soft strip and demolition of Penrose (Building 18)