Barratt London: Saturday 23rd October

Barratt London will carry out following activities on Saturday 23rd October:

  •  2no. forklifts moving materials – site wide

  •  Brickwork & blockwork at B1A ,B2A, C1A, C2A, L&M

  •  Ground works to parcel E1A & E2B, Gate M

Bricklayers will cease all works at 1pm. Ground workers and Barratt staff will remain on site till 3:30pm and carry out low noise activities.

Location of Barratt London works

Lisa Baker