A look ahead for March 2021
Hospital Buildings (Delivered by Sir Robert McAlpine)
Ongoing construction of concrete frame work to Forensic Hospital Building
Ongoing façade installation to Forensic and Non-Forensic buildings
Fitout and masonry works are ongoing to Non-Forensic building
Fitout works to Forensic and Energy Centre to commence early March
Civil and Infrastructure (Delivered by Sir Robert McAlpine)
Limited works in the park area due to ground being too wet. Trimming of boundary shrubs will commence to allow for muck shifting in early April 2021.
Ongoing works to Road 1 located east of Storey Building. Works scheduled for 6 months and traffic management setup to divert traffic to the east of Elizabeth Newton.
Ongoing works to Road 2 - Storey carpark access road. Access to carpark will be closed. Road construction commenced outside the nursery and gym buildings, but uninterrupted access will be maintained for both parties.
Ongoing works to Road 3 - adjacent to the new Care Home (Plot H).
Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)
Pile mat works to parcels B-E and L&M
Piling is expected to begin on 8 March and run for approximately 10 weeks in parcels B-E and 2 weeks in L&M.
Marketing suite works have commenced to L&M with the cabin arriving on 10 March ready for launch at Easter.
The existing hoarding line will be removed w/c 10 March
The new bellmouth to the sales area in parcels L&M will commence next week.
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Sales Areas are now plastered and fitting out now to commence.
Structural alterations continue in Jasmine Tower also now in Lupin and Rose Towers.
Externally the stone, brick and roof repairs continue with scaffold to the Central Tower to commence to be removed.
The clock face on the Central Tower to be restored and numerals redecorated
Works to the front lawn to progress with repairs to the existing drainage and preparation of the roadway.