A look ahead for May 2022
Hospital Buildings (Delivered by Sir Robert McAlpine)
Trinity (Non-Forensic) building’s façade is now complete. The Shaftesbury (Forensic) façade is still ongoing but nearing completion.
There are ongoing fitout works to Shaftesbury and Trinity hospital buildings.
Mechanical and Electrical works ongoing to both Shaftesbury and Trinity buildings.
All scaffolding has now been struck on both the Trinity and Shaftesbury buildings.
Civil and Infrastructure (Delivered by Sir Robert McAlpine)
Park works progressing with earthwork movements to complete topsoil profiling works in the final areas for phase 1. Footpath construction to the Southern boundary to tie into the existing footpath in the existing car park in St Georges Grove complete, with tarmac works this month.
Tree and shrub planting is ongoing in the park area.
Construction is progressing outside Mayfield Nursery and Gymnastics Club and both new hospital buildings, but uninterrupted access will be maintained for both parties through Share Garden.
Works to progress hard landscaping on Springfield Drive is ongoing.
Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)
Plot M
Internal works complete
Hard landscaping and soft landscaping to be complete and area opened
Plot L
Internal works continue
All scaffold to be removed
Service connections being worked on to footpath on Glenburnie Road
Balconies installed
Remove all hoarding
Plot B – C
Internal works progress
Balcony install
Hard landscaping continues and will be complete to B within the next month
Soft landscaping commence
C1A scaffold strike to commence
C2A to progress to roof
Plot E1/E2
Superstructures continue up to 1st and second floors
Plot D2
First ground floor slabs to be installed
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Externally roofing works ongoing to Primrose.
Progressive scaffold strike
External Hard and Soft Landscaping ongoing
Masonry repairs & cleaning
Preparation works for new welfare and storage areas.
Internally, units and communal areas in the Jasmine link, Lupin Tower and Lupin link final snagging and handover.
Commissioning works ongoing
External service distributions to continue to both Phases 1 and 2.
Substation transformers to be installed.
First Fix Drylining, M&E & carpentry to Primrose & Central Wing
Phase 2 drainage works
Phase 2 asbestos removal complete.
Phase 2 soft strip & demolition ongoing.
Phase 2 structural alterations ongoing.
First occupations are planned for end of May.
New care home facility - Plot H (delivered by Lawrence Baker)
Complete installing the glazing to the external windows.
Commence the feature panels to the side of the windows.
Complete plaster boarding and skimming throughout.
We currently plan to remove the crane from site on the 19th May.
Commence removal of scaffold to the Eastern Block – currently around a month late.
The ground works are due to recommence on site on the 23rd May.
Continue throughout the building with second fix joinery & M&E.