A look ahead for August 2022
Hospital Buildings (Delivered by Sir Robert McAlpine)
Trinity (Non-Forensic) building’s façade is now complete. The Shaftesbury (Forensic) façade is still ongoing but nearing completion.
There are ongoing fitout works (including painting and decorating) to Shaftesbury and Trinity hospital buildings that are ongoing but nearing completion in some areas
Mechanical and Electrical works ongoing to both Shaftesbury and Trinity buildings which includes commissioning and testing.
Civil and Infrastructure (Delivered by Sir Robert McAlpine)
The park is completed and handed over for its maturing period.
Construction is progressing outside Mayfield Nursery and Gymnastics Club and both new hospital buildings, but uninterrupted access will be maintained for both parties through Share Garden.
The hard landscaping on Springfield Drive and Chapel Square is nearing completion with progressing the installation of the granite, paving, lighting columns and trees.
Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)
Block M: Partially occupied. To be fully occupied by C.O.B 05/08/22.
Block L: Completion to Block & Handover to be complete throughout August.
Block L&M external soft & hard-landscaping to be completed by late August.
Block B1 – C1: Hard & Soft Landscaping progressing, with completion to blocks/houses & handover to all 3 parcels over next 4-6weeks, including all soft & hard landscaping.
Block C2: Internal fit-out ongoing, with anticipated completion October.
E1 & E2: Superstructure now on 2nd floors throughout, roofing works finishing on E1B mid-August.
D2 – Ground floor now installed with superstructure works now underway.
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Phase 1
First Fix, Close Up, Plaster, 2nd Fix, Decoration and Finals to apartments
Completion of apartments and communal areas
Scaffold strike to remaining blocks
External finishes
Hard and soft landscaping
Legal completions
Occupations
Phase 2
Demolition works ongoing
Drainage and services
Scaffold erection and adaptions
Masonry repairs and cleaning
Window Repairs
Structural alterations and repairs
Roofing works
New care home facility - Plot H (delivered by Lawrence Baker)
Complete installing the remaining windows to the lower ground floor
Complete external ground works in preparation of Tarmac in September
Continue with installing the incoming services, water, electricity, and district heating
Commence the external brick clean
Install the railings and glass to the external podium area on the south elevation.
Continue with internal finishes including decoration and flooring.
Commence installing the passenger lifts.