A look ahead for July 2023

Hospital Buildings (Delivered by Sir Robert McAlpine)

  • Following the handover of the Trinity building, there are final fitout works (including painting, decorating and furnishings) to Shaftesbury hospital building.

  • Mechanical and Electrical works are still ongoing to the Shaftesbury building which includes commissioning and testing prior to handover.

Civil and Infrastructure (Delivered by Sir Robert McAlpine) :

  • The park will open on 5th July 2023 .

  • Public access is opened on Springfield Drive and Chapel Square.  Car parks in the new hospitals are open.

  • Plot A – SRM’s new welfare is now up and running and will be located here until the end of the year.

  • The entrance to Burntwood Lane is closed and access is provided further north on Burntwood Lane.  The new road construction and junction works is completed.  We are waiting on Wandsworth Council to sign off.

  • Muck movement is ongoing to allow the Belvedere to commence.  Pathways will start imminently.

  • Ronald Gibson House plot remediation has commenced to allow this plot to be handed over to the plot developer.

  • Ruskin lane works progressing, which will allow the G1 bus to return to Springfield Village at the end of the Summer.

  • Harewood House demolition is progressing, with soft strip completed and the removal of the licenced asbestos is progressing.  Demo to start mid July 2023.

  • Switchover works are being coordinated with the Trust for Storey, Elizabeth Newton, Morrison, Shaftesbury and Phoenix Buildings.

  • Park C muck shift works progressing and the BT diversion is completed, to allow the attenuation pond to be excavated.

  • Road 4; Lapidge Drive is progressing with drainage and services.

SRM Works Location drawing for July 2023

Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)

  • Blocks L, M, B1, C2a, B2a, C1a are fully occupied

  • Blocks B2, C1 handed over to PA Housing, occupations ongoing

  • Blocks C2 handovers completing, occupations

  • Occupations ongoing to E1a, E1c and E1b

  • Service install ongoing to E2 parcel blocks

  • Hard landscaping to E2 parcel blocks

  • Scaffold dismantle ongoing to E2b and E2c blocks

  • RC frame works ongoing to D1a shaft walls.

  • Superstructure work, incl. roof joist work progressing to parcel D2c.

Conversion of listed main building to residential - Plot S (delivered by City & Country)

Phase 1

  • Decoration and Finals to remaining apartments.

  • Completion of apartments and communal areas.

  • External finishes.

  • Legal completions.

  • Occupations to Primrose Tower and Central east Wing

  • Completed on 51no plots to date. 

Phase 2

  • Structural alteration works ongoing to the Engineering Block and Boiler House.

  • Scaffold erection and adaptions.

  • Structural alterations and repairs.

  • Roofing works.

  • Re-Facing of brickwork elevations.

  • Masonry repairs and cleaning.

  • Window refurbishment

  • Internal fit out ongoing to ‘Kitchen Block’ area.

Area of Responsibility Plan

Lisa Baker