A look ahead for August 2023
Hospital Buildings (Delivered by Sir Robert McAlpine)
Following the handover of the Trinity building, there are final fitout works (including painting, decorating and furnishings) to Shaftesbury hospital building.
Mechanical and Electrical works are still ongoing to the Shaftesbury building which includes commissioning and testing prior to handover.
Civil and Infrastructure (Delivered by Sir Robert McAlpine)
The park (area B) is open.
Public access is opened on Springfield Drive and Chapel Square. Car parks in the new hospitals are open.
Plot A – SRM’s new welfare is now up and running and will be located here until the end of the year.
The entrance to Burntwood Lane is closed and vehicle access is provided further north on Burntwood Lane. Pedestrian access is now available along the north of the opened park. The new road construction and junction works is completed. We are waiting on Wandsworth Council to sign off.
Pathways have commenced in Park A. The belvedere drainage blanket is progressing.
Ronald Gibson House plot remediation is progressing to allow this plot to be handed over to the plot developer at the end of the month.
Ruskin lane works progressing, which will allow the G1 bus to return to Springfield Village in September, once the entrance to Burntwood Lane is open.
Plot P&Q will be handed over to the plot developer end of the month.
Harewood House demolition is progressing, with the removal of the licenced asbestos completed and demolition having commenced. Demolition will progress until October 2023.
Switchover works are being coordinated with the Trust for Storey, Elizabeth Newton, Morrison, Shaftesbury and Phoenix Buildings. Will be completed this month.
Park C muck shift works progressing and the attenuation pond is being excavated. Pathways to start imminently.
Road 4; Lapidge Drive is progressing with services and kerbs. Tarmac is planned for the end of the month.
Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)
Blocks L, M, B1, C2a, B2a, C1a are fully occupied
Blocks B2, C1 handed over to PA Housing, occupations ongoing
Blocks C2 handovers completing, occupations
Occupations ongoing to E1a, E1c and E1b
Service install ongoing to E2 parcel blocks
Hard landscaping to E2 parcel blocks
Scaffold dismantle ongoing to E2b and E2c blocks
RC frame works ongoing to D1a shaft walls.
Superstructure work, incl. roof joist work progressing to parcel D2c.
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Phase 1
Decoration and Finals to remaining apartments.
Completion of apartments and communal areas.
External finishes.
Legal completions.
Occupations to Primrose Tower and Central east Wing
Completed on 55no plots to date.
Phase 2
Structural alteration works ongoing to the Engineering Block and Boiler House.
Scaffold erection and adaptions.
Structural alterations and repairs.
Roofing works.
Re-Facing of brickwork elevations.
Masonry repairs and cleaning.
Window refurbishment
Internal fit out ongoing to ‘Kitchen Block’ area.