A look ahead for June & July 2024
Hospital Buildings (Delivered by Sir Robert McAlpine)
Both Hospital Buildings are open for use.
Civil and Infrastructure (Delivered by Sir Robert McAlpine)
The park (area B) is open.
Public access is opened on Springfield Drive and Chapel Square. Car parks in the new hospitals are open.
The entrance to Burntwood Lane is OPEN for both vehicle and pedestrian access.
Park area A is nearing completion with soft landscaping, play equipment and resin works to pathways being completed. The pavilion is nearing completion too. Park area A is due to open October 2024, after a period of maturing.
Harewood House plot to be handed over to the House Developer in June 2024.
Park C works are progressing with soft landscaping, gym stations and pathways. Park area C is due to open October 2024, after a period of maturing.
District heating works down to X,Y,Z plot is progressing.
Road 4; Lapidge Drive is completed and open for access to everyone.
The last substation build within the development is completed outside Phoenix Building. Infrastructure works is progressing to allow energisation in July 2024.
Residential Phase - Plots B-E and L&M (delivered by Barratt London)
D2C Occupied
E1 Occupied
E2 Occupation to commence in July
D1A Superstructure complete, scaffold strike in progress, Balcony install to commence early July, internal fit out has commenced
D1B, Occupations to commence in July
D1C Occupations to commence in July
D2B Occupations to commence in July
D2A 3rd floor slab install late June
D parcel Road (Cherry mews) topping to commence late June
Conversion of listed main building to residential - Plot S (delivered by City & Country)
Phase 1
Complete
Phase 2
Scaffold adaptions and strike
Structural alterations and repairs
Roofing works to Orchid Wing
Re-Facing of brickwork elevations
Masonry repairs and cleaning
Window refurbishment
Commence fit out to Engineering Tower
Test and commissioning
Finals and Inspections to the Kitchen Block and Dormitory apartments
Handovers and completions within Kitchen Block, Engineering Tower & Dormitory Wing
Internal fit out ongoing to Dormitory and Orchid wing
Hard & Soft Landscaping.
Next phase of new build residential Plots G, P, Q and F (delivered by London Square)
Block P
Continuing with the basements to the houses.
Commencing the retraction of the sheet piles to the basement excavations on the houses.
Commencing super structure brickwork to the apartment block
Installing the beam and block floor to the apartment block.
Commencing setting out & 1st lift scaffold.
Block Q
Commencing the basement excavation to the houses.
Commencing basement slabs and walls to the houses.
Commencing ground beams to block Q1 & Q2 apartment block
Block G
Existing substation has been deenergised and removed and the new substation energised and in use.
Installing the beam and block floor to the G2 & G3 apartment block.
Continuing with the ground beams on G4
Commencing brickwork to G2/3.
Block F
SRM to handover block F to LSQ, with demolition and pile mat works to commence tail end of June with the piling contractor lined up to start 22 July 2024