A look ahead for June & July 2024

Hospital Buildings (Delivered by Sir Robert McAlpine)

  • Both Hospital Buildings are open for use.

Civil and Infrastructure (Delivered by Sir Robert McAlpine)

  • The park (area B) is open.

  • Public access is opened on Springfield Drive and Chapel Square.  Car parks in the new hospitals are open.

  • The entrance to Burntwood Lane is OPEN for both vehicle and pedestrian access.

  • Park area A is nearing completion with soft landscaping, play equipment and resin works to pathways being completed.  The pavilion is nearing completion too.  Park area A is due to open October 2024, after a period of maturing.

  • Harewood House plot to be handed over to the House Developer in June 2024.

  • Park C works are progressing with soft landscaping, gym stations and pathways.  Park area C is due to open October 2024, after a period of maturing.

  • District heating works down to X,Y,Z plot is progressing.

  • Road 4; Lapidge Drive is completed and open for access to everyone.

  • The last substation build within the development is completed outside Phoenix Building.  Infrastructure works is progressing to allow energisation in July 2024.

SRM Works Location drawing for June/July 2024

Residential Phase - Plots B-E and L&M (delivered by Barratt London)

  • D2C Occupied

  • E1 Occupied

  • E2 Occupation to commence in July

  • D1A Superstructure complete, scaffold strike in progress, Balcony install to commence early July, internal fit out has commenced

  • D1B, Occupations to commence in July

  • D1C Occupations to commence in July

  • D2B Occupations to commence in July

  • D2A 3rd floor slab install late June

  • D parcel Road (Cherry mews) topping to commence late June

Conversion of listed main building to residential - Plot S (delivered by City & Country)

Phase 1 

Complete

Phase 2

  • Scaffold adaptions and strike

  • Structural alterations and repairs

  • Roofing works to  Orchid Wing

  • Re-Facing of brickwork elevations

  • Masonry repairs and cleaning

  • Window refurbishment

  • Commence fit out to Engineering Tower

  • Test and commissioning

  • Finals and Inspections to the Kitchen Block and Dormitory apartments

  • Handovers and completions within Kitchen Block, Engineering Tower & Dormitory Wing

  • Internal fit out ongoing to Dormitory and Orchid wing

  • Hard & Soft Landscaping.

Next phase of new build residential Plots G, P, Q and F (delivered by London Square)

Block P

  • Continuing with the basements to the houses.

  • Commencing the retraction of the sheet piles to the basement excavations on the houses.

  • Commencing super structure brickwork to the apartment block

  • Installing the beam and block floor to the apartment block.

  • Commencing setting out & 1st lift scaffold.

Block Q

  • Commencing the basement excavation to the houses.

  • Commencing basement slabs and walls to the houses.

  • Commencing ground beams to block Q1 & Q2 apartment block

Block G

  • Existing substation has been deenergised and removed and the new substation energised and in use.

  • Installing the beam and block floor to the G2 & G3 apartment block.

  • Continuing with the ground beams on G4

  • Commencing brickwork to G2/3.

Block F

  • SRM to handover block F to LSQ, with demolition and pile mat works to commence tail end of June with the piling contractor lined up to start 22 July 2024

External CGI from London Square Apartment overlooking Springfield Park

Area of Responsibility Plan

Lisa Baker