Hospital Buildings (Delivered by Sir Robert McAlpine)

  • Following the handover of the Trinity building, there are final fitout works (including painting, decorating and furnishings) to Shaftesbury hospital building.

  • Mechanical and Electrical works are still ongoing to the Shaftesbury building which includes commissioning and testing prior to handover.

Civil and Infrastructure (Delivered by Sir Robert McAlpine)

  • The park is completed and handed over for its maturing period.

  • Public access is opened on Springfield Drive and Chapel Square.  Car parks in the new hospitals are open and car park B is closed to allow Park C preparation works to progress.

  • Plot A – SRM’s new welfare is now up and running and will be located here until the end of the year.

  • The entrance to Burntwood Lane is closed and access is provided further north on Burntwood Lane. This is to allow the new road construction to progress and the junction works will commence in April 2023.

  • The pavilion building in Park A is progressing and muck movement is progressing. 

  • Ronald Gibson House demolition is progressing with soft strip and demolition will commence early April 2023.

  • Harewood House demolition has commenced with the asbestos survey.  Soft strip will commence in April and demolition will start mid May 2023.

  • Park C works hoarding works completed and preparation works, ahead of muck shifting is progressing.

Map of where the SRM works are taking place on the site

SRM Works Location drawing for April 2023

Next phase of new build residential - Plots B-E and L&M (delivered by Barratt London)

  • Blocks L and M are fully occupied

  • Block B1 partially occupied (houses and duplex units predominantly), April handovers to the remaining plots

  • Blocks B2, C1 and C2 second fix works, decorations and internal snagging ongoing

  • Block C2a is fully occupied

  • Blocks E1 and E2 – External façade works ongoing with the first fix fit out to E1 parcel

  • Groundworks continue to E1 parcel blocks/houses

Conversion of listed main building to residential - Plot S (delivered by City & Country)

Phase 1

  • Plaster, 2nd Fix, Decoration and Finals to remaining apartments.

  • Completion of apartments and communal areas.

  • Scaffold removal to remaining areas.

  • External finishes.

  • Legal completions.

  • Occupations

  • Completed on 43no plots to date.

Phase 2

  • Soft strip and demolition works ongoing.

  • Drainage and services.

  • Scaffold erection and adaptions.

  • Structural alterations and repairs.

  • Roofing works.

  • Re-Facing of brickwork elevations.

  • Masonry repairs and cleaning.

  • Drylining first fix M&E First fix to the Kitchen block units.

The Meadowcroft Care Home - Plot H (delivered by Lawrence Baker)

The Meadowcroft care home opened its doors to residents in February 2023. The former care home Ronald Gibson House, which sits in Plot G, will commence demolishment this month.